Does mountaintop removal coal mining cause only minimal
damage to West Virginia’s hills, forests and streams?
On Monday, a federal appeals court will consider that
question. The 4th Circuit Court of Appeals is scheduled to
hear arguments in the latest legal effort to more strictly
regulate Appalachian strip mining.
In the case, the Bush administration and the coal
industry are challenging rulings by U.S. District Judge
Joseph R. Goodwin in Charleston.
Goodwin blocked the U.S. Army Corps of Engineers from
approving new mountaintop removal valley fills through a
streamlined permit process that allows little public
scrutiny.
In a series of rulings starting July 8, 2004, Goodwin
said the corps never concluded that valley fills have
minimal impact on the environment. Without that finding, the
Clean Water Act does not allow the corps to authorize the
fills through streamlined permit reviews, Goodwin ruled.
Goodwin ruled in response to a case brought in October
2003 by the Ohio Valley Environmental Coalition and two
other groups, Coal River Mountain Watch and the Natural
Resources Defense Council.
In a brief filed with the 4th Circuit earlier this year,
lawyers for those groups outlined the findings of a
41/2-year government study of mountaintop removal:
If past, present and future disturbance is combined,
strip mining will impact more than 1.4 million acres of the
region’s land.
In this case alone, 11 specific permits challenged by
environmentalists would bury 26 miles of streams, court
records show.
“It is difficult to imagine how any agency, no matter how
delusional, could conclude that this amount of destruction
is minimal or insignificant,” environmental group lawyers
Jim Hecker and Joe Lovett told the 4th Circuit.
In mountaintop removal, coal companies use explosives to
blast apart entire hilltops and uncover valuable, low-sulfur
coal seams. Huge trucks and dozers roll in and load up the
coal. Leftover rock and dirt — the stuff that used to be the
mountain — is shoved into nearby valleys, burying streams.
As the practice grew in the mid-1990s, citizen opposition
grew into public protests and a series of lawsuits and
permit challenges.
Twice in the past four years, the Richmond, Va.-based 4th
Circuit — dubbed the most conservative appeals court in the
nation by The New York Times — has thrown out U.S. District
Court rulings aimed at limiting mountaintop removal. Both of
the previous rulings were by now-deceased U.S. District
Judge Charles H. Haden II.
Before they can open new surface mines, coal operators
must obtain several permits from state and federal
regulators. Among those is a permit from the corps for the
actual filling of streams with mining waste.
Under the federal Clean Water Act, the corps can issue
two types of fill permits: individual permits and
nationwide, or general, permits.
Individual permits cover specific fill proposals. Before
issuing them, the corps must conduct a “case-by-case
evaluation” of potential environmental effects.
General permits cover categories of activities, and are
issued on a statewide, regional or nationwide basis. When it
issues general permits, the corps spells out the general
conditions that a particular category of activity should
meet. Then, companies seek authorization for specific
projects. If they promise to meet the general conditions,
their projects are authorized with much less review than
individual permits.
Under the law, general permits are allowed to be used
only for activities that “will cause only minimal adverse
environmental effects when performed separately, and will
have only minimal cumulative effects on the environment.”
For years, the corps approved coal mining valley fills
through a general permit called Nationwide Permit 21, or NWP
21.
On July 8, 2004, Goodwin agreed with environmental group
arguments that the corps had never found the effects of
valley fills to be minimal. Goodwin blocked the corps from
approving new valley fills through NWP 21. About a month
later, on Aug. 13, Goodwin expanded the ruling to block
valley fills that had received a permit, but where work had
not yet begun.
In its appeal, the Bush administration argued that
Goodwin overstepped his authority in tossing the corps’
decision to use NWP 21 for valley fills. Generally, federal
courts are required to defer to environmental agency legal
interpretations unless actions are unreasonable or plainly
erroneous.
“This approach by the corps strikes the best balance
between environmental concerns and Congress’ desire that a
more streamlined and general permit for categories of
activities be made available, and that the wheel, as it
were, not be reinvented each time a permit is issued — in
other words, compelling the mining industry to seek
individual permits in all instances for valley fills,” the
corps lawyers wrote.
Corps lawyers also argue that their agency in fact does a
case-by-case review of valley fill proposals that apply for
NWP 21 approval to ensure that they would have minimal
impacts.
Goodwin rejected this position, noting that it allows
valley fill decisions to avoid public review and comment
that would be required under applications for individual
permits.
“By combining features of both individual and general
permitting in NWP 21, the corps allows an activity with the
potential to have significant effects on the environment to
be permitted without being subject to public notice and
comment or the other procedural hurdles to authorization,”
Goodwin wrote in his July 8 ruling.
In legal briefs filed with Goodwin, coal industry lawyer
Bob McLusky argued that the case was “the third attempt by
environmental organizations to halt coal mining in Central
Appalachia.
“Although the first two attempts proved ultimately
unsuccessful, the coal industry still struggles to recover
from the substantial disruptions to the permitting process
caused by the litigation,” McLusky wrote.
Bush administration officials have agreed.
During a speech to West Virginia business leaders in
September 2004, James Connaughton chairman of the White
House Council on Environmental Quality, said that Goodwin’s
ruling “put a halt to work West Virginia coal miners do for
their communities.”
Thomas J. Sansonetti, an assistant U.S. attorney general,
said in a prepared statement that the decision “will
substantially curtail production of West Virginia coal that
is low in sulfur and, therefore, less polluting.”
But since January alone, the corps has issued more than
20 individual permits for coal-mining stream fills,
according to agency records.
At the same time, 2005 coal production through Sept. 10
in West Virginia is up about 2.6 percent over the same
period last year, according to the U.S. Department of
Energy.
In court papers, McLusky said that Arch Coal officials
believed that Goodwin’s ruling would hamper their efforts to
obtain new permits and keep mining coal in West Virginia.
But in conference calls with industry stock analysts,
Arch CEO Steve Leer has said that his company won’t have
many problems with the individual permit process.
“Arch has been anticipating that this could be a likely
outcome for a number of years,” Leer said just weeks after
Goodwin’s ruling.
“I think it will make it more difficult for people to get
permits,” Leer added.
“It will lengthen the time of the permit process, which
is already lengthy. But we’ve built that in and made it part
of our modus operandi.”
Just two months ago, Massey Energy President Don
Blankenship said that his company was not having problems
getting the permits it needs to continue mining.
“Overall, we are OK with permits,” Blankenship said in a
conference call with industry analysts. “The speed with
which we’re getting them has not changed much, but some of
the larger ones we’ve gotten have put us in good shape. I
know of no significant issues that we have.”
To contact staff writer Ken Ward Jr., use e-mail or call
348-1702.