|
This news story originally provided by
The Charleston Gazette
Federal regulators have given final approval to the largest
mountaintop removal-mining permit in West Virginia history.
Last week, the U.S. Army Corps of Engineers issued a Clean Water
Act permit for Arch Coal Inc.’s Spruce No. 1 Mine in Logan County.
The move comes nearly eight years after a federal judge blocked
the original permit, and as environmental groups and industry
officials are waiting for two other major court rulings on
mountaintop removal.
Corps officials approved a “dredge-and-fill” permit that allows
the Spruce Mine to bury nearly seven miles of streams in the
Pigeonroost Hollow area of Logan County, near Blair.
Col. Dana R. Hurst, the corps district engineer in Huntington,
approved the permit in a 41-page record of decision signed Jan. 22.
Arch Coal has scaled back the operation, from the 3,113 acres
originally approved to 2,278 acres, according to corps permit
documents and state Department of Environmental Protection records.
It would likely still rank as the largest permit ever issued in
West Virginia, said DEP spokeswoman Jessica Greathouse. One other
Arch Coal permit, for its Hobet 21 Westridge Mine, is slightly
larger, but only because of area that was added after the original
operation was approved, Greathouse said.
The original Spruce Mine permit would have buried more than 10
miles of streams, and mined nearly 55 million tons of coal.
In a detailed mine study finalized in September, the corps said
the new version reduces environmental impacts, while allowing Arch
Coal to reach about 75 percent of its coal reserves.
“The applicant made additional modifications to further avoid and
minimize impacts to the environment, while satisfactorily meeting
the purpose and need for the project,” the permit study said.
Still, the mine’s final approval is likely to stir controversy,
and probably bring more court action to try to stop it.
Joe Lovett, a lawyer for the Ohio Valley Environmental Coalition
and the West Virginia Highlands Conservancy, said that those groups
are “considering all of their options and may challenge it in
court.”
Just a week before the permit was approved, the wife of one of
the Spruce Mine’s most vocal opponents died.
Sible Rose Wheatley Weekley, 62, of Blair, died on Jan. 15. She
and her husband, James Weekley, lived along Pigeonroost Branch and
filed the original lawsuit that helped launch the fight against
mountaintop removal.
Kim Link, a media spokeswoman for St. Louis-based Arch Coal, did
not return a phone call Monday.
As originally proposed, the Spruce Mine would have extended Arch
subsidiary Hobet Mining Inc.’s Dal-Tex complex east across W.Va. 17
into Pigeonroost Hollow. In 1998, that proposal was at the heart of
the first in a series of federal court lawsuits that sought to curb
mountaintop removal mining.
In March 1999, then-Chief U.S. District Judge Charles H. Haden II
issued a preliminary injunction blocking the corps’ permit for the
mine. Haden said that the company — and the agency — had illegally
“segmented” the operation into smaller phases to avoid doing a
lengthy study called an Environmental Impact Statement, or EIS.
Haden issued two other, broader rulings to more strictly regulate
mountaintop removal, but both were overturned by the 4th U.S.
Circuit Court of Appeals in Richmond, Va.
Haden’s ruling to block the Spruce Mine also led to a series of
protests by the United Mine Workers, whose members hoped to continue
their jobs at Dal-Tex onto the new permit.
Now, Arch Coal has transferred the mine to its Mingo Logan Coal
Co. subsidiary and plans to operate with non-union workers, said UMW
spokesman Phil Smith.
The Spruce Mine is perhaps the only mountaintop removal mine to
undergo an EIS for its Clean Water Act permit from the corps.
Both sides of the mountaintop removal controversy are waiting for
a ruling from U.S. District Judge Robert C. Chambers in Huntington
in a case that seeks to force all mines to have an EIS before they
are approved.
Also, U.S. District Judge Joseph R. Goodwin is considering
whether to reopen a separate case over the way the corps approves
most mines through a streamlined permit process.
Historically, the corps has almost always allowed mine operators
to use this streamlined process to obtain “nationwide” or “regional”
permit approvals that involve less rigorous regulatory review.
Goodwin had blocked that maneuver by the corps, but the 4th
Circuit overturned his ruling. Now, lawyers for environmental groups
want to reopen that case on different grounds.
When the corps has forced operators to obtain more detailed
“individual permits,” the agency has generally concluded that the
mining would cause only minor environmental damage, a move that let
companies avoid conducting an EIS before mining. Chambers has been
asked to stop that process, forcing an EIS to be performed on all
mines.
To contact staff writer Ken Ward Jr., use e-mail or call
348-1702.
|